Your common Northstowe questions answered

We have put together a list of some of the most common questions that we get asked about various aspects of Northstowe. We hope that this page is helpful. 

If you have a question and answer that you would like added to this page, please send the details through to communications@scambs.gov.uk

We will add further questions and answers to this page in future. This page was last updated on Tuesday 17 January 2023.

When is each permanent community facility coming forward?

With regards to the timing of each building coming forwards, as of 16 January 2023, here’s what we can tell you at this stage: 

  • Phase one Sports Pavilion: Work has started on site, and we expect it to be completed in Summer 2023. 
  • Interim Community Facility:  A planning application to provide a temporary community centre has been submitted with a decision expected in March at the earliest. If given the go ahead, the building would be placed on land owned by the Council next to The Green, on Pathfinder Way, alongside the area earmarked for Northstowe’s permanent community centre. The large single-storey modular building includes plans for a generous lobby with kitchenette and toilets, storage, and would have space for three offices, an NHS room, and two large community rooms which can be used for a wide range of activities for all ages including: 
    • Community cafes 
    • Baby and toddler groups 
    • Private hire for events such as birthday parties 
    • Children and youth activities 
    • Art workshops and events 
    • Meeting spaces for sport and activity groups 
  • Phase one Community Centre: The aim is for the Council to submit a planning application in Summer 2023, with an anticipated delivery date of 2025. 
  • Phase two Civic Hub: We are currently working with partners and stakeholders to produce a detailed design brief ahead of going out to procurement later this year. 
  • Phase two Sports Pavilion: Work has not yet commenced owing to the delivery of this facility coming in a later stage of Northstowe's development. It is anticipated that this pavilion will likely be delivered when around 2,500 homes at Northstowe are occupied. 

When will the first shops and cafes open?

Homes England is seeking a partner to deliver Central One. This is an initial phase of the Northstowe town centre. It is planned to include a market hall and a convenience store, as part of a mix of uses appropriate to a town centre setting. It also includes space for the Civic Hub building, including library, health and community space. Proposals will be worked up during the next year. It is hoped that construction work will then start before the end of 2023. Facilities will then open to residents as an early deliverable, within a four-year build programme.

When will the roads be adopted?

Roads, cycle paths and footways should all be complete by the end of 2024. The adoption of roads is currently expected to be at the end of 2025, following a 12-month maintenance period.

What provision is there for GP services for residents?

Currently, Northstowe residents can register with the local GP surgery at Willingham Medical Practice. Going forwards, the Civic Hub, planned as part of Phase Two of Northstowe, will provide healthcare space, including GP services.

When will the Phase Two Waterpark open?

Homes England hope to open the waterpark by the end of the year.

Questions answered at recent Northstowe Community Forums

The following questions have been answered during recent Northstowe Community Forums.

When will the roads and cycle paths in Phase 1 be completed?

The issue is that the construction lorries inevitably clip corners and destroy curb stones – that is why there are so many that are loose in Northstowe. Because of this it does not make sense to finish the roads to their final surface, as it would only take a few months before they were in need of repair. 

The Greater Cambridge Shared Planning Team has investigated different possible routes for the construction traffic, but once lorries enter Northstowe there are four separate housebuilders’ compounds as destinations, which means that whatever route they take, almost every major road in Northstowe is subject to at least some lorry traffic. 

Individual housebuilders are responsible for their own parcels, including roads. 

Roads, cycle ways and footways should all be complete by the end of 2024. The adoption of roads will then be end of 2025, following a 12-month maintenance period.

What is the latest regarding the link road between Phase One and Longstanton Park and Ride?

Cambridgeshire County Council have appointed a contractor for the construction of the link road and the path link into the waterpark from the Park and Ride site. 

Work has now begun on site and is expected to be complete by the end of the year.

We were requested to make a fee payment before completion of our property which would go towards the first year’s fee, but we still received an invoice from Greenbelt.

Once Greenbelt has secured a contract with the relevant house builder, any monies the house builder has collected will be passed to Greenbelt and Greenbelt will provide a credit to residents.

What is the latest on the Civic Hub?

The Civic Hub will provide health, library and community space. Progress has been hampered as key partners have dealt with the pandemic. However, consultants have helped draw together a blueprint of requirements for the building and a report is expected shortly. 

Any updates on missing post?

The issue of missing post has been escalated to Royal Mail and they are investigating. 

How do I report something that I am concerned about?