Histon, Impington and Orchard Park A14 information

The planned road closures for this week can be viewed online and this page is updated weekly.

Please note that it is sometimes necessary for Highways England to undertake unscheduled closures to undertake emergency repairs.

We have created a poster to help spread the word about the A14 upgrade updates that are available to residents of Histon, Impington and Orchard Park. You can download the poster.

Who to contact to find out more?

Highways England have dedicated people who can be contacted as your first point of call for further information on works being undertaken in a given section of the route, or if you have any concerns about the works:

Sections 4 & 5: Swavesey to Milton

Engagement@thea14.com

Alternatively, you can contact Highways England on the A14 helpline on 0800 270 0114 - This will be answered by a team member during site hours 8am - 5pm, Monday to Friday and messages can be left at other times. Further updates as the scheme progresses can be found on the Highways England website.

For night works the rapid response number is 01480 220281 - This will be answered by a team member during the hours of 9pm - 6am.

Updated 20 September 2019

Below shows the 10 day look ahead for night time working:

 

 

Scroll for more

Date

Location

Description of Activity

Comments

Noise impact Rating

Mitigation Measures

Friday 20 September

Junction 33 East Bridge

WB Verge (adjacent Girton Bridge)

Junction 32 EB exit slip road

WB Junction 32 - NIAB

EB Junction 32 - Jct 33

NIAB - Junction 33

Junction 32

Duct trough works - Placement of trough slabs

Installation of Environmental Barrier

Narrow widening (excavation, place & compact stone)

Installation of street lighting & CCTV columns

(incl' excavation)

Gantry Modifications

Herbicide Application

 

Medium

High

Keep raised voices to a minimum

Minimise vehicle idling engines

Reduce amount of reversing by maintaining a one way system

Friday 20 September 56 hour weekend closure Junction 32 Gyratory. B1049 North closed at junction 32. Junction 32 Eastbound entry and exit sliproads closed. 

 

High

High

 

Saturday 21 September

reconstruction and surfacing 

Keep raised voices to a minimum

Minimise vehicle idling engines

Reduce amount of reversing by maintaining a one way system

Sunday 22 September 

 

 

Monday 23 September

 

Tuesday 24 September 

B1049 Northbound

Junction 33 East Bridge

WB Verge Junction 33

Girton OB - West side

EB verge adjacent Impington Bridge

Installation of DNO supplies and electrical cabinets

Duct trough works - Placement of trough slabs

Complete works to Verge i.e. VRS Install

Prep embankment for Environmental barrier

RS5.8 backfill to abutment walls

 

Medium

High

Keep raised voices to a minimum

Minimise vehicle idling engines

Reduce amount of reversing by maintaining a one way system

B1049 Northbound

Junction 33 East Bridge

WB Verge Junction 33

Girton OB - West side

EB verge adjacent Impington Bridge

Installation of DNO supplies and electrical cabinets

Duct trough works - Placement of trough slabs

Complete works to Verge i.e. VRS Install

Prep embankment for Environmental barrier

Retaining wall,  backfill to abutment walls

 

Medium

High

Keep raised voices to a minimum

Minimise vehicle idling engines

Reduce amount of reversing by maintaining a one way system

Wednesday 25 September 

B1049 Northbound

Junction  33 East Bridge

WB Verge Junction 33

Girton OB - West side

EB verge adjacent Impington Bridge

Installation of DNO supplies and electrical cabinets

Duct trough works - Placement of trough slabs

Complete works to Verge i.e. VRS Install

Prep embankment for Environmental barrier

Retaining wall,  backfill to abutment walls

 

Medium

High

Keep raised voices to a minimum

Minimise vehicle idling engines

Reduce amount of reversing by maintaining a one way system

Thursday 26 September

B1049 Northbound

Junction  33 East Bridge

WB Verge Junction 33

Girton OB - West side

EB verge adjacent Impington Bridge

Installation of DNO supplies and electrical cabinets

Duct trough works - Placement of trough slabs

Complete works to Verge i.e. VRS Install

Prep embankment for Environmental barrier

Retaining wall,  backfill to abutment walls

 

Medium

High

Keep raised voices to a minimum

Minimise vehicle idling engines

Reduce amount of reversing by maintaining a one way system

Friday 27 September

B1049 Northbound

Junction  33 East Bridge

WB Verge Jct 33

Girton OB - West side

EB verge adjacent Impington Bridge

Installation of DNO supplies and electrical cabinets

Duct trough works - Placement of trough slabs

Complete works to Verge i.e. VRS Install

Prep embankment for Environmental barrier

Retaining wall,  backfill to abutment walls

 

Medium

High

Keep raised voices to a minimum

Minimise vehicle idling engines

Reduce amount of reversing by maintaining a one way system

Friday 27 September 56 hour weekend closure Junction 32 westbound exit slip road.

Reconstruction of exit slip road.

Medium

High

Keep raised voices to a minimum

Minimise vehicle idling engines

Reduce amount of reversing by maintaining a one way system

Saturday 28 September
Sunday 29 September

 

Complaints

Highways England has a dedicated email address for the local community to raise issues and complaints relating to the works being undertaken in the Histon and Impington / Orchard Park area.

You can also contact us we will investigate and work with Highways England to address the issue.

Should you wish to make a formal complaint to us, it has a formal complaints procedure.

Was this web page helpful?

The form contains errors