9.3 Milestones for Priority 2 - Northstowe and Growth Areas
Our aim is that by March 2007 we will have: -
- the planning framework for Northstowe essentially in place through progress on the LDF and we will be confident of approving the planning application and Section 106 Agreement in June 2007.
- a clear Council project plan showing our aims for Northstowe, how we will achieve them and how this will impact on Council resources.
- agreement on the provision required for community facilities and governance at Northstowe.
- a clear way ahead for the provision of energy generation at Northstowe.
Table 18 - Northstowe and Other Growth Area Milestones
|
# |
Milestone |
By when |
PFH |
Responsible Officer |
|
7 |
Northstowe: completion of Local Management Organisation Study |
Q2 06 |
CS&CP |
Jane Thompson |
|
8 |
Civic Hub proposals completed, including specification. |
Q2 06 |
CS&CP |
Simon McIntosh |
|
9 |
LDF - Commence Public Examination |
Q3 06 |
P&ED |
Keith Miles |
|
10 |
Medium Term project plan – programme for all growth areas with resource and workforce projections |
Q3 06 |
Leader |
Greg Harlock |
|
11 |
All Community facility and service proposals completed including specifications, phasing and developer contributions required |
Q4 06 |
CS&CP |
Simon McIntosh |
|
12 |
Northstowe Draft S.106 statement complete |
Q4 06 |
P&ED |
Jane Green |
|
13 |
Northstowe: completion of Town Centre strategy |
Q4 06 |
P& ED |
Keith Miles |
|
14 |
LDF - Adoption by Council |
Q3 07 |
P&ED |
Keith Miles |
|
15 |
Northstowe Energy and Utilities: to complete a detailed risk assessment and feasibility study to enable the Northstowe Sustainable Energy Partnership to be progressed. |
Q1 07 |
CS&CP |
Cameron Adams |