9.3 Milestones for Priority 2 - Northstowe and Growth Areas

Our aim is that by March 2007 we will have: - 

  • the planning framework for Northstowe essentially in place through progress on the LDF and we will be confident of approving the planning application and Section 106 Agreement in June 2007.
  • a clear Council project plan showing our aims for Northstowe, how we will achieve them and how this will impact on Council resources.
  • agreement on the provision required for community facilities and governance at Northstowe.
  • a clear way ahead for the provision of energy generation at Northstowe.

Table 18 - Northstowe and Other Growth Area Milestones

#

Milestone

By when

PFH

Responsible Officer

7

Northstowe: completion of Local Management Organisation Study

Q2 06

CS&CP

Jane Thompson

8

Civic Hub proposals completed, including specification.

Q2 06

CS&CP

Simon McIntosh

9

LDF  - Commence Public Examination

Q3 06

P&ED

Keith Miles

10

Medium Term project plan – programme for all growth areas with resource and workforce projections

Q3 06

Leader

Greg Harlock

11

All Community facility and service proposals completed including specifications, phasing and developer contributions required

Q4 06

CS&CP

Simon McIntosh

12

Northstowe Draft S.106 statement complete

Q4 06

P&ED

Jane Green

13

Northstowe: completion of Town Centre strategy

Q4 06

P& ED

Keith Miles

14

LDF  - Adoption by Council

Q3 07

P&ED

Keith Miles

15

Northstowe Energy and Utilities: to complete a detailed risk assessment and feasibility study to enable the Northstowe Sustainable Energy Partnership to be progressed.

Q1 07

CS&CP

Cameron Adams

 